Scheduling around the HVAC replacement
We come in before the HVAC installer, not alongside. The order that works is sampling, a written list of each duct run and material, removal and cleanup, and then the installer’s start date. We give you the lab results to hand to the installer, so they know which remaining materials, if any, must not be cut.
Houses and buildings with up to four units are outside the air district rule. For five or more units, or a commercial space, the rule applies, and the notice goes to the air district at least 10 working days before removal begins. Either way the crew works to Cal/OSHA’s asbestos standard. From 100 square feet of asbestos material we send Cal/OSHA a job notice before starting, and smaller jobs are reported on a Report of Use.